Stay Informed
Follow us on social media accounts to stay up to date with REHVA actualities
Michele Zinzi | Kirsten Engelund
Thomsen | Heike Erhorn-Kluttig | Marko Jacimovic |
ENEA Italian National Agency for New Technologies,
Energy and Sustainable Economic Development, Italy | Aalborg Universitet
– SBi, Denmark | Fraunhofer Institute for Building Physics, Germany | Building and Civil Engineering Institute ZRMKGradbeniinštitut ZRMK,
Slovenia |
BenedettaMattoni | Ove Christen Mørck | MarjanaŠijanec-Zavrl | Bernd Utesch |
ENEA Italian National Agency for New
Technologies, Energy and Sustainable Economic Development, Italy | Kuben Management A/S, Denmark | Building and Civil Engineering Institute ZRMKGradbeniinštitut ZRMK,
Slovenia | ABG Frankfurt Holding, Germany |
The Project
CoNZEBs (Solution sets for the cost reduction of new
Nearly Zero-Energy Buildings) is funded by the European Commission in the
framework of the Horizon 2020 Program to identify, asses life cycle cost and
analysis, and disseminate technological solutions able to reduce the
construction costs of new nearly zero energy multi-family houses. Among the
different activities, a work package was bound to identify potential cost
reduction in the design and construction process (hereafter D&CP). This
article presents the main outcomes of the activities, which were structured in
the following phases:
·
Identification
of the current D&CP in the EU member states, with obvious focus on the
project participant countries (Denmark, Germany, Italy, Slovenia);
·
Identification
of common boundary conditions and areas for possible cost reductions;
·
Involvement
of stakeholders through questionnaires and interviews to identify most
promising approaches, methods and tools for D&CP;
·
Provide
exemplary solutions able to optimise and reduce costs in the overall process.
The full
report "D3.1 Assessment and exemplary solutions for cost reduction in the
design and construction process" will be public on the project website (www.conzebs.eu),
where all the results of the activity will be available in detail.
Current
costs in the design process for minimum requirements and nearly zero energy
multi-family houses were analysed in participant countries, while a wide literature
review was carried out to assess such costs in other member states. Design fees
can be determined in three main ways: percentage of the building cost,
pre-defined fixed fees, time charge based on hourly rates, depending on:
the country, the size of the project, and its complexity.
Results in
the participant countries were significantly different, in fact the share of
design fees in respect to the overall construction project costs was identified
as follows:
·
Denmark
8–15%
·
Germany
13% (median value)
·
Italy
7–9%
·
Slovenia
3–4%
It has to
be noted that only in Italy, the survey evidenced an increase of design costs
for nearly zero-energy buildings in respect to the minimum requirements ones;
while no differences were detected in the other countries.
Analysing
the construction process, it was found out that the area for cost reduction
could be focused on the preliminaries (or indirect costs), which are costs not
explicitly related to the specific items of measured work but mainly related to
the construction site "life cycle" (i.e. plants, accommodation,
temporary services, rents, transport, scaffolding, and insurances). Few data
were available among the participant countries, in Italy a small survey proved
shares in the 5–10% range; more data were collected at EU level, proving that
preliminary accounts for 10–15% of total construction project.
In the next
phase common boundary conditions and topical issues were screened: the main
actors involved in the process, specific issue for the social housing, the
construction site organisation and the worker skill, the compliance of work
execution, supporting instruments. It was found out that very few data from the
field are available for what concerns the impact of several measures in
reducing costs in the D&CP.
In order to
better understand the feeling and the expectations of the main actors involved
in the D&CP, two questionnaires were developed and sent around to related
categories. The questionnaire for the designers and planners addressed the
following main issues:
·
Awareness
about and experience with the design and planning of NZEBs.
·
Method
of calculating the costs for design and planning.
·
Solutions
to reduce design and planning costs or to reduce costs during the whole
construction process (to be tailored at national level).
·
Experience
and impact of the long-term maintenance costs.
The questionnaire for the designers and planners addressed the following main issues:
·
Awareness
and experience of NZEBs.
·
Adopted
process to execute the construction works.
·
Magnitude
and causes for cost variations in respect to the planned costs.
·
Internal
process to reduce construction costs.
·
Solutions
to reduce overall construction costs (to be tailored at national level).
Also, the
housing companies were involved in the survey. Alternative to the
questionnaire, interviews with targeted actors were carried out.
Designers
and planners detect in the integrated planning the most profitable instrument
to reduce overall costs for the design and construction process on average in
the four countries, see Figure 1. In Germany the most voted solution
is avoiding underground spaces for cellars and parking. Average values are
scored for the other proposed solutions. BIM is seen as a potential area for
cost reduction, especially in Italy and in Slovenia, while the optimisation of
common area in multi-family houses is not considered significantly. External
staircases and more compact building forms are considered as profitable
solutions to optimise the construction costs in Germany.
Concerning
contractors and construction companies, the most profitable solution is the
efficient quality control in each phase of the process to avoid extra cost for
rework, the latter being a critical issue emerged from the questionnaire
results, see Figure 2. Also, industrialisation in
construction components reach a high score. Some solutions, as BIM and skilled
workers, show a strong dependence on the specific country in terms of cost
reduction expectations. It was observed that potential solutions for cost
reduction are more positively evaluated in Italy and Slovenia than Germany and
Denmark, a situation that might also depend on how the market has already
implemented cost efficiency measures in the different countries.
Figure 1.
Answers of designers and planners about solutions to reduce D&CP costs.
Figure 2.
Answers of contractors and construction companies about solutions to reduce
D&CP costs.
Exemplary
solutions were identified and analysed to show potential areas for cost
reduction in the D&CP. It has to be underlined that they might not be of very
general validity, since many factors can affect the final results; conversely,
they show the potentialities for cost reduction, intrinsic in the overall
process, which needs to be addressed by the involved actors in a holistic
approach to the building construction project.
The
investigated solutions demonstrate the cost effectiveness in terms of
technology costs (material + labour), as well as the capacity of reducing the
time for the execution of the works, with additional savings at construction
site preliminaries.
The first
example is the building facade made of large autoclaved aerated concrete (AAC)
blocks, which allows completing the single layer facade in only one workflow
with a thermal transmittance as low as to 0.15 W/m²K, instead of the two
or three cycles needed with other envelope technologies. Figure 3 shows construction works with AAC blocks. A comparison versus a
reference clay brick layer plus an ETICS facade was carried out for an Italian
multi-family house, showing 19% reduction costs and a significant 47% reduction
of the construction time.
Another
example, coming from Denmark, is the case for roof integrated PV systems: the
underlying construction is the same as for other roof types, but the finishing
layer is made of PV modules overlapping both by length and width the
construction below, see Figure 4. This solar roof is easy and fast
to mount in one simple workflow; it is obviously more expensive than a
conventional roof but compared to the situation in which a traditional PV
system has to be added, it leads to about 28% cost savings. Moreover, the
construction time is reduced by 50%.
Figure 3.
Example of construction works using autoclaved aerated concrete blocks. © Xella Italia S.r.l, Italy
Figure 4.
Exemplary application of PV integrated roof. © EnnogieApS, Denmark
These
solutions proved that decisions taken during the design phase can positively
affect the overall construction process cost, even though they may require
small cost increase during the design and planning phase. A German study and
application, as an example, proved the positive impact of external staircases
in a multi-family house, with the concurrent reduction of the building external
surface to heated volume ratio from 0.5 to 0.37 m-1, and estimated 26% energy savings for space
heating. Actualising the cost incurred at the construction time, the identified
solution also leads to façade construction cost savings of 60 €/m² of living
area. Figure 5 shows a view of the building.
Figure 5.
Example of multi-family house with external staircases. © Fraunhofer Institute
for Building Physics
The focus
was here on BIM (Building Information Modelling), generally defined as a digital
planning and project monitoring method, based on a shared virtual dynamic
building modelling, including a detailed database of continuously synchronised
data. While this solution is still seen as not cost effective in relatively
simple construction projects such as multi-family houses, a US study showed a high
return of investments by BIM in a ten projects survey, with economic savings
directly to the process in the 0–1.5% range (but one case with 14% savings).
First data from the field in Europe were documented in two UK projects; here the
economic benefit due to BIM were estimated to be 1.5 to 3%.
While most
of the construction project costs are allocated for the construction phase
(materials + labour) the performed activities evidenced areas for the cost
reductions also in the design and construction process. Expectations and
opinions of the involved actors differ from country to country depending on a specific
priorities and maturity of the construction market. However, several strategies
and solutions can be implemented with the general trend of moving the
construction project from a traditional to an industry-like approach, where the
accurately planning and management of all phases and the minimisation of the
construction site lifetime will play a crucial role.
The CoNZEBs project has received funding from the European
Union's Horizon 2020 research and innovation programme under grant agreement No.
754046.
Follow us on social media accounts to stay up to date with REHVA actualities
0