Keywords: arctic dwellings, mechanical ventilation, heat recovery, inspection, performance assessment

 

Jakub Kolarik
Martin Kotol
Technical University of Denmark, Department of Civil and Mechanical Engineering, Denmark
jakol@dtu.dk
Technical University of Denmark, Department of Civil and Mechanical Engineering, Denmark

 

Greenland’s new airtight, energy-efficient homes widely use mechanical ventilation with heat recovery. Harsh arctic conditions challenge the systems on many fronts. It is crucial to ensure their proper performance throughout their lifetime. A new inspection methodology aims to identify faults before they compromise systems’ performance and occupants’ comfort and health.

Challenging ventilation in Arctic homes

Greenland’s extreme Arctic climate places high demands on the construction and operation of buildings and their systems. Long winters with temperatures dropping below −30°C and intense winds are followed by short summers with long-lasting daylight and a lot of solar gains. Such conditions require highly insulated and airtight building envelopes that ensure thermal comfort at low energy demand. Airtight envelopes result in a need for ventilation systems able to provide continuous air exchange. Ventilation must handle freezing, dry air, and prevent frost and snow accumulation. At the same time, the systems must be robust and have minimal maintenance requirements as remote communities often lack skilled personnel. In general, residential buildings in Greenland lack proper ventilation, which leads to poor indoor air quality (IAQ) and moisture-related problems (Kotol et al. 2014). Due to weather conditions, opening windows is limited and occupants often seal fresh air valves to prevent cold draft. Application of mechanical ventilation is usually limited to bathroom exhaust fans and kitchen hoods. However, Greenlandic building practices are undergoing significant changes. Newly constructed dwellings (Figure 1) often feature mechanical ventilation systems with heat recovery (MVHR), which offer solutions to the previously mentioned issues. MVHR systems are being installed in new and renovated dwellings, even though they are not required by the building code (Kotol 2021). Their performance relies on proper installation, commissioning, and operation. This is valid not only for arctic dwellings. Challenges with ensuring proper installation and stable performance of mechanical ventilation systems are well known across climate zones (Balvers 2012, Janssens et al. 2013). In Greenland, the limited availability of experienced personnel and the absence of clear guidelines in building legislation pronounces the situation. To ensure the performance of mechanical ventilation systems, a robust solution is to conduct regular inspections that identify potential faults and deviations from the intended performance. Consequently, when problems are identified, an appropriate action can be taken by the homeowner or an authorized technician.

The objective of the project conducted at the Technical University of Denmark (DTU) is to develop a methodology for performance evaluation of mechanical ventilation in Greenlandic dwellings. The methodology should comprise technical inspections including necessary measurements as well as key performance indicators and procedures for data analysis. The project aims to map the situation related to real-life performance of MVHR in Greenlandic homes, focusing on new and renovated buildings. Dissemination of results to local stakeholders, mainly installers and ventilation designers, is an integral part of the project. This article introduces the project’s approach and presents results after its initial phase.

Figure 1. Airtight building envelopes and mechanical ventilation with heat recovery become common in Greenland

Inspection methodology

To ensure the performance of an MVHR system in operation it is important to assess the actual operating conditions and identify potential failures or deviations from intended performance. Therefore, the project focuses on on-site inspections combined with long-term measurements. The issue of inspections of ventilation systems is not a new topic. The technical study conducted by international experts at the request of the European Commission addressed this issue in relation to the so called EPBD Directive (Directive (EU) 2018/844), see Durier et al. (2020). The report gives a detailed summary of regulations, standards and guidelines related to inspections of stand-alone ventilation systems. It is clear from the study that when measurements are prescribed, they comprise airflows, fan electricity consumption and ductwork airtightness. The focus is much less on Indoor Air Quality (IAQ), despite its outmost importance in dwellings. We used available literature and standards and focused on adaptation of that knowledge into Greenlandic context. European standard EN 14134:2019 (CEN 2019) deals with inspections of residential ventilation systems. We used the standard as basis for designing the inspection and performance evaluation procedure comprising four main parts: pre-check, functional check and measurements, special measurements and reporting (Figure 2). The terminology, types of measurements and technical checks are following the standard. The performance assessment has several parts (see Figure 2): technical visit - including short, structured interview with homeowners; system and house inspection facilitated by specially developed checklist and including spot measurements of airflows, fan power and assessment of internal leakage; long-term measurements of operational parameters of the air handling unit (AHU) lasting 14 days. Finally, there is a short briefing visit to deliver the report to the occupants including oral explanation of main findings and, where necessary, assistance with an action plan to mitigate failures.

Figure 2. Structure of the performance assessment methodology

The project started with brainstorming sessions and discussions with Greenlandic design engineers, which, together with a literature study, resulted in the preliminary proposal for the inspection methodology. The project will evaluate the methodology in three phases, each involving two single family homes. We conducted the first two phases in December 2025 and March 2026. The following sections present examples of the obtained results. The third phase is planned for winter and spring 2027.

Results from pilot tests

Test houses

Pilot tests in the first phase took place in two houses situated in Sisimiut, Greenland. Sisimiut, with a population of more than 5500 inhabitants, is the second-largest city in Greenland. It is situated on the west coast, 75 km north of the Arctic Circle. The houses were single-family homes built in 2013 (Figure 3- left) and 2021. The houses have heavily insulated timber construction and oil-based heating system. Fresh air is delivered by balanced mechanical ventilation units with rotary heat exchangers. Houses were occupied by families of four (two adults and two children).

Pre-check and functional measurements

Two members of the research team conducted the inspections. As a part of the pre-check, we conducted short (max. 15 min.), structured interview with one adult living in the house. A Google forms-based questionnaire filled out by the interviewer was used to collect the data. Paper based checklist served for collecting data during the technical inspection. The checklist included evaluation of overall and ductwork cleanliness, ductwork layout and condition, information about air terminals, AHU, heat recovery, filters and controls. Measurements of airflow rate and direction at air terminals were also noted in the checklist. Comparing occupants’ answers in the interview with data collected during technical inspection revealed that occupants’ satisfaction with the ventilation system did not fully represent the system’s technical condition. For example, in one of the houses, the occupants were very satisfied with the ventilation. At the same time, the inspection showed that there was a failure in the supply part of the system. The failure resulted in no supply airflow into the house, which went unnoticed by the occupants. There was also discrepancy in relation to cleanliness of the system. The observed filter condition did not reflect statements of the occupants about frequency of filter changes (Figure 3). Moreover, contrary to our expectations, it was not possible to collect design materials and drawings. So, the lesson learned is that the inspector needs to ask about systems metadata during the interview.

Figure 3. Left and centre - Condition of supply air filters in the inspected houses, right – placement of long-term data loggers on the air handling unit

The pilot inspections led to changes in the originally designed checklist. This comprises addition of visual analogue scales for assessment of AHU and ductwork cleanliness. We also increased the amount of input fields regarding air terminals. There were simply more air terminals than expected (one per room). We used a hot-wire anemometer-based flow meter to determine air flows through all air terminals. In the first house no supply airflow was measured, while total exhaust airflow amounted to 58.1 m³/h. The inspection of the AHU revealed defect in the control system disturbing the operation of the supply fan. In the second inspected house, total exhaust and supply airflows were 70 m³/h and 69 m³/h respectively.

Special measurements

The measurements defined in addition to the framework given by EN 14134:2019 (CEN 2019) are called special measurements. In the suggested methodology, special measurements represent IAQ data collected in so-called reference room as well as air temperatures and relative humidities (RH) at all sides of the air handling unit (intake, supply, extract and exhaust) and measurements of the unit’s electricity use over a fourteen-day period. We applied work done by Poirier et al. (2022) and Laverge et al. (2025) to define the key performance indicators (KPI) related to IAQ. Table 1 presents the KPIs and their values for the second pilot house.

Table 1. Example of IAQ related KPIs determined in the second pilot house.

KPI description

KPI Value

Indoor Air Quality

Normalized cumulative CO2>1 000 ppm

10.7 [ppm]

Mean of CO2>1 000 ppm ± SD

1 238 ± 170 [ppm]

95th percentile of CO2concentration

960 [ppm]

Normalized cumulative RH < 25%

0.6 [%]

Mean of RH < 25% ± SD

23.5 ± 1.1 [%]

Percentage of time with RH > 60%

0 [%]

Normalized cumulative PM2.5concentration

2.4 [µg/m³]

Heat recovery efficiency and energy use

Supply temperature ratio/efficiency - ηts(1)

0.84

Humidity ratio/efficiency - ηxs(1)

0.19

Specific fan power - SFPv(1)

3.4 kW/m³s

(1) Determined from measurements conducted during inspection in the house; analysis of long-term measurements is still ongoing.

 

The data confirm that AHUs with rotary heat exchangers also recover part of the moisture from the extract air. This has a positive effect in Greenlandic conditions where the moisture content is often lower than 1 g/kgdry air (Kotol 2021) leading to low relative humidity levels in the heated supply air. The ventilation system also provided a reasonable amount of fresh air, the 95% percentile of the CO2 concentration was 959 ppm, so concentrations were lower than 1000 ppm for 95% of the time. Table 1 also shows temperature and humidity efficiency (sometimes also called temperature/humidity ratio) of the heat recovery and the AHU’s specific fan power (SFP). The ηxs of 19% illustrates previously mentioned humidity recovery. The SFP was close to the requirement by the current Greenlandic building regulation (Government of Greenland 2006) (3.2 kW/m³s), but it was too high with respect to the manufacturer’s documentation, which stated value of 1.8 kW/m³s. Such value of SFP would be flagged for further inspection.

Conclusion and outlook

We have conducted the first two phases of the project focused on development of inspection procedure for performance assessment of heat recovery ventilation in Greenlandic dwellings. The pilot phase in two houses resulted in adjustments in the inspection procedure, originally based on the standard EN 14134:2019 (CEN 2019). Data from the consequent phase including two additional homes are under analysis. The further work will focus on utilization of long-term measurements, which, besides the IAQ KPIs, can also provide information about operational stability of the AHU. For example, we aim to use the capacity ratio method developed by Smith and Kolarik (2022) to assess air flow balance across the unit. Long-term data will also provide information about performance of AHU’s frost protection. In the final phase of the project, we will focus on determination of limit values for the KPIs, and the finalized methodology will be tested by ventilation technicians from practice.

Acknowledgement

The authors would like to thank Bjarne Saxhofs Fund for supporting the presented research.

References

Balvers, J., Bogers, R., Jongeneel, R., van Kamp, I., Boerstra, A., van Dijken, F., “Mechanical ventilation in recently built Dutch homes: technical shortcomings, possibilities for improvement, perceived indoor environment and health effects”, Archit. Sci. Rev. 55(1), 4–14, 2012, https://doi.org/10.1080/00038628.2011.641736

CEN, “EN 14134:2019 Ventilation for buildings—Performance measurement and checks for residential ventilation systems”, European Committee for Standardization, 2019.

Durier, F., Wouters, P., De Strycker, M., Guyot, G. , Sherman, M., Leprince, V., Urbani, M., “Technical study on the possible introduction of inspection of stand‑alone ventilation systems in buildings”, Publications Office of the European Union, Luxembourg, 2020, ISBN 978‑92‑76‑19259‑6, https://doi.org/10.2833/621790

Government of Greenland, “Building Regulations 2006”, Department of Infrastructure, Housing, Rural Districts and Emergency Management, 2006.

Janssens, A., Carrié, F.R., Durier, F., (eds.), “Securing the quality of ventilation systems in residential buildings: existing approaches in various countries”, INIVE, Belgium, 2013, ISBN 2‑930471‑43‑3.

Kotol, M., Rode, C., Clausen, G., Nielsen, T.R., “Indoor environment in bedrooms in 79 Greenlandic households”, Build. Environ. 81, 29–36, 2014, https://doi.org/10.1016/j.buildenv.2014.05.016

Kotol, M., “Current ventilation strategies in Greenlandic dwellings”, J. Build. Eng. 39, 102283, 2021, https://doi.org/10.1016/j.jobe.2021.102283

Laverge, J., Jones, B., Rojas, G., Abadie, M., Qin, M., Guyot, G., Kolarik, J., (eds.), “D3 – Methods and tools for the rating of IAQ management strategies”, INIVE eeig, 2025, ISBN 978-2-930471-80-8.

Poirier, B., Kolarik, J., Guyot, G., Woloszyn, M., “Design of residential ventilation systems using performance‑based evaluation of indoor air quality: application to a Danish study case”, E3S Web Conf. 362, 09004, 2022, https://doi.org/10.1051/e3sconf/202236209004

Smith, K. M., Kolarik, J., “Smart ventilation toward an assessment of airflow imbalance and supply temperature set-points”, Proceedings of 42nd AIVC Conference, Rotterdam, The Netherlands, 639-640, 2022.

Jakub Kolarik, Martin KotolPages 22 - 26