Keywords: Commissioning; ventilation systems; indoor climate; REHVA Guidebook 27.
|
Risto Kosonen |
Professor Aalto Universityristo.kosonen@aalto.fi |
The EPBD requires zero-emission buildings in the future. The starting point is to reduce energy consumption in accordance with the principle of energy efficiency first. The EPBD requires non-residential buildings to be equipped with measuring and control devices intended for monitoring and regulating indoor air quality. In practice, this can be done with demand-based ventilation and its automation system.
Complex building services systems require special expertise in design, contracting and further in the operation phase. The optimal operation of complex systems also requires ensuring the cooperation of different component systems. Currently, there are gaps in training and, in addition, a lack of guidance on designing more complex systems and, above all, ensuring continuous operation, which make it difficult to create well-performing systems.
The right amount of ventilation is important for both healthy indoor air and energy efficiency, as for example ventilation accounts for an estimated 15–20% of Finland’s total energy use. The importance of ventilation is also highlighted by the fact that ventilation accounts for approximately 30–40% of the energy consumption of commercial buildings. This energy consumption of ventilation can be reduced by up to 50% when ventilation is controlled according to actual need of occupants compared to ventilation systems operating with constant air flows.
In addition, it is good to remember that the economic significance of indoor climate is quite high in terms of both human productivity and health. Deterioration in indoor climate can cause multiple costs in relation to the energy consumption of the property. Previous studies have found that in premises designed for high indoor climate classes, the average user dissatisfaction with air quality and thermal conditions is 30% (Abdul-Wahab, 2011). There are several reasons for this: poor commission, user layout changes in the premises, design and installation faults, etc. Often the problems are small and can be easily fixed if they are detected.
Typically, in demand-based system, ventilation airflows are controlled based on a schedule, a room occupancy detector, a temperature sensor and indoor air quality sensors. The most commonly used indoor air quality sensors are carbon dioxide (CO2) sensors, which estimate the number of people in the premises. Adjustment based on the number of people is important, as the typical occupancy rate in many office buildings is only around 30–40%.
The air flow rate control of rooms or terminal units can be implemented in a modulated manner between the minimum and maximum air flows of the room, based on pre-defined air flow rates, or as an on/off control in maximum/normal air flow rates. The air flow settings of demand-based systems can be designed for individual rooms, zones or open areas such as open-plan offices.
The flaw of complex systems is often a challenge. These problems in ventilation are not new, as complex systems require special expertise at different stages of the project. Chilled beam systems became popular in the 90s, when it was found that controlling water is simpler than controlling air flows and makes air-water system more popular, especially in Nordic counties.
The literature review presents the following solutions and corrective actions to address issues in buildings equipped with demand-based ventilation systems (Zhou et al., 2022). These were related to the processes of building design, installation, commissioning and operation e.g.:
· Improving the training of designers, contractors and maintenance personnel
· Thorough commissioning tests before the occupancy period
· Updated and detailed design documents after commissioning phase
· Utilizing building automation system for continuous monitoring
· Improving the appreciation and motivation of maintenance personnel
· Regular inspections and re-commissioning
The biggest challenge lies in the implementation process. The solution for managing problems is continuous commissioning. It is generally understood that quality control only applies to the commission and hand-over phase. However, functional assurance of systems should start from the design phase and cover the entire life cycle.
Indoor climate classification has been used in design for several decades. A similar process is also needed to monitor the indoor climate of occupied buildings. Regarding the indoor climate conditions, at least the room air temperature, carbon dioxide concentration and pressure difference of the zones to control air flow balance between supply and exhaust must be verified.
In this way, the emergence of most indoor air problems can be prevented in advance and at the same time the requirement of the Energy Directive is implemented. It has been suggested that systematic inspections can reduce the energy consumption of a building by up to 15-40% and most system problems and deficiencies are found early enough in inspections carried out during different process phases.
REHVA guidelines (REHVA, 2019) emphasize that the functional assurance process covers the entire life cycle. The guideline assumes that all HVAC systems and components in a building are designed, installed, tested, maintained and operated in accordance with the requirements and objectives set by the user organization/investor.
The tasks of the continuous commissioning process are divided into three phases in a construction project: activities before construction, work during construction phase and tasks after construction during the operation phase. The following is a list of key activities during the different phases.
Pre-construction planning
· Goal setting and owner project requirements
· Indoor climate targets are set
· Selection of ventilation system
Design
· Selection of components and subsystems
· Control strategy of systems
· Commissioning planning
Tendering
· Commissioning requirements are attached to the commissioning documents.
· The components that are specified in design are purchased
Installation
· Correct components received
· All components installed correctly in right location
Functional tests for subsystems
· Component/subsystem checks
· Sensors
· Setpoints for each sub-systems
Testing of the whole system
· Operation of the entire system in all control modes (winter, mid-season and summer)
· Operating parameters are measured and compared with the readings from the building management system
Seasons
· Finding the right operating parameters for each system in each season and operating mode
Continuous inspection
· Collecting data on performance indicators (indoor environmental quality, user satisfaction, energy and water use) and comparing them with target values
Operational planning
· Annual operational review of all key performance indicators and performance measurements (automatic or manual)
· Building site visit
· Planning for maintenance, retrofits and renovations
Regular operational inspection during the entire life-cycle of the building has clear benefits: guaranteed indoor climate conditions and energy efficiency of building technical systems. It can therefore be stated that all parties benefit from well-functioning building services systems.
This means that indoor air conditions are healthy, and people feel comfortable in spaces. When ventilation systems work properly, the property owner benefits from higher rental income, lower energy bills and building operating costs. When employees and residents feel healthier, they can work more productively. A building that functions in this way can also charge higher rent, which benefits the property owner. The value of the property also increases when it is energy efficient and comfortable.
REHVA. (2019). REHVA Guidebook No. 27 - HVAC Commissioning Process.
Sick Building Syndrome in public buildings and workplaces (2011). Abdul-Wahab, Sbah A. (Ed.) 1st edition,011. Lill. 591 p. Springer.
Zhao, W., Kilpeläinen, S., Bask, W., Lestinen, S., Kosonen, R. (2022). Operational Challenges of modern Demand-Control Ventilation Systems: A Field Study. Buildings 12, no. 3: 378. https://doi.org/10.3390/buildings12030378