EN 15459-1:2017 provides a method for economic evaluation procedures for building, building components and energy systems. The aim of this standard is the support for the decision taking on technologies applied in building construction and renovation process and help to find the cost optimal solution by aggregation of present and future costs in two main indicators described in this standard that are:
· global costs
· payback period of investment.
Global costs are the sum of the present value of the initial investment costs, annual running costs and replacement costs referred to the starting year as well as disposal costs if applicable. If the lifespan of the last replacement cost exceeds the end of calculation period, the final value of a component at the end of calculation period is determined and referred to the beginning of the calculation period. The global costs approach allows to find the optimal option from comparison of unlimited number of solutions.
Payback period is the time when the investment costs are balanced with the monetary savings occurring. The payback period is used to compare the cost efficiency of investment against the reference case. Usually the solution under consideration is compared to a reference situation that can be situation before investment in case of renovation or the minimum requirements in case of new building construction. EN 15459-1:2017 provides calculation for the discounted payback period.
The potential applications of the methods described in the EN 15459-1 are:
· evaluation of economic performance of an overall design of the building,
· evaluation of economic feasibility of specific energy related investment,
· comparison of energy saving options and finding the cost efficient and cost optimal solutions.
An important part of this standard is the informative data for components provided in Annex D referenced also by the Commission delegated regulation (EU) No. 244/2012 supplementing EPPBD for calculating cost-optimal levels of minimum energy performance requirements for buildings and building elements. EN 15459-1 after revision in 2017 is in line with this Regulation in terms, definitions and calculation methodology and therefore this training could also support the cost optimal level of energy performance calculation by national authorities.
The informative data for components provided in Annex D and referenced in Regulation No. 244/2012 are:
· the life span of components in years (Min – Max),
· annual maintenance cost (% of initial investment),
· disposal cost (% of initial investment).
Connection with other EPB standards is based on delivered energy per energy carrier calculated according to Overarching standard EN ISO 52000-1 that is input for energy costs calculation. For finding the cost optimal solution also link with the primary energy calculated according to EN ISO 52000-1 is recommended.
The CEN-CE teaching materials on EN 15459 are focused on presentation and understanding of:
· the structure of data considered in economic calculation;
· required inputs;
· calculation method (formulas);
· resulting outputs;
· recommendation for interpretation of results, reporting and use in design practice.
The specific of this standard is wide variety of level of detail and uncertainty of some inputs as it presents an aggregation of present and future costs over a long calculation period (20 – 50 years). Therefore, the reporting and interpretation of the results needs special attention. Sensitivity analysis on most important inputs and consideration of different scenarios for future development is recommended in CEN-CE training for practical use of this standard and failure risk mitigation.
The structure of the costs considered in calculation are detailed in Figure 1. They are in line with the Commission delegated regulation (EU) No. 244/2012 for calculating cost-optimal levels of minimum energy performance requirements.
The flowcharts help to understand the calculation steps (Figure 2) and the spreadsheet allows the demonstration of calculation and influence of different input parameters. Example of definition and presentation of input data in spreadsheet is shown in Figure 3 and of output in Figure 4.
Figure 1. The structure of costs considered for economic evaluation of energy related investment.
Figure 2. Example of flowchart for calculation of global costs.
Figure 3. Example of input data in spreadsheet.
Figure 4. Example of method output presentation in spreadsheet for economic evaluation for two options.
All input data shall be consistent and shall be based on local conditions at the time of the analysis. Some optional informative default values and options can be presented in National Annex A if it exits or default inputs for CEN option can be find in Annex B to standard.
The description of scenarios (solutions) under consideration with the boundaries specification is needed before input data collection. The scenarios have to be defined and described by:
· the time (duration) of calculation (whole life cycle, economic lifespan);
· physicallimits (whole building, part of the building, only building system);
· costs considered (overall costs, only selected specific cost items for specific systems or products);
· financial data (discount rate, inflation)
· evolution of prices (energy, products, services, human operation)
· scenarios for maintenance and replacement cost
Economical results are closely related to the project under consideration. The NZEB are costly and the potential solutions to achieve NZEB should be carefully evaluated. The sensitivity of results increases depending on the complexity and number of parameters taken into account in calculation and it may be difficult to come to the conclusion.
Part of CEN-CE training is focused on the sensitivity analysis for the most influencing input parameters with important uncertainty. The CEN–CE certified expert should be aware about the dependency of the results on a good estimation of all input parameters used in calculation with regards to their future developments (e.g. the prices evolution).
The different scenarios consideration is recommended to be calculated and presented as the results. This will allow the risk mitigation of uncertainty of input data e.g. by consideration of the most-likely, optimistic and pessimistic scenario. The most influencing parameters and choices in economical evaluation to be considered are:
·
the discount rate (lower highlights benefits from the investment
in energy savings);
·
prices of energy carriers (must be consistent for a place and time of
the calculation);
·
the evolution of energy prices (increase will favour the energy related
investment);
·
lifespan of components that indicates the period for replacement and new
investment needed. Cheaper product may have a shorter lifespan and could lead
finally to higher global costs. Correct and consistent way of estimation of
life span of components and measures is important for comparison between products and solutions.
This is why the revision of the data for components (life span, annual
maintenance and disposal costs) listed in Annex D has been agreed by CEN/TC 228
and inputs from manufactures will be needed.
Examples of sensitivity analysis on some of most influencing parameters are in Figure 5 and an example of combination of influencing parameters in different scenarios is in Figure 6.
Figure 5. Example of sensitivity analysis on the most influencing parameters.
Figure 6. Examples of different scenarios (pessimistic, likely and optimistic) for most influencing parameters.
The global
costs approach allows comparison of unlimited number of solutions.
The payback
period is used to compare the cost efficiency of the solution under
consideration to a reference situation. For existing buildings, the reference is
usually the actual state (doing nothing). For new buildings, the reference
could be a building that satisfies the minimum requirements of the national
regulation.
The cost
efficiency of proposed solution is usually ensured if the life span of
investment is greater than or equal to the payback period.
Examples of reporting outputs and application in the decision making process for cost efficiency and cost optimality of solutions are in Figure 7 and Figure 8.
a) Payback period | b) Global costs |
Figure 7. Example of reporting the outcome from calculation of Payback period and Global costs
Figure 8. Example of more detailed reporting of global costs for two different solutions.
As shown
in Figure 6 not only global costs should be
the main driver for the recommended cost optimal solution. The primary energy and the energy class in EPC are important aspects for
climate commitments and future obligations for building owner that could bring
him the non-energy benefits or cause losses (subsidies, green/brown taxes,
attractiveness, better/worse IAQ, secure for increase of energy prices). Therefore,
in the case of similar global costs for different solutions the solution with
lower primary energy should be recommended.
Graphs with
the annual costs as presented in Figure 9 allow to schedule the investment in
renovation based on the life span of components taking into account the running
costs and periodic replacement costs as well as the evolution of energy and
components prices. These graphs could be part of renovation roadmaps and building renovation
passports as
they can indicate the years with important investments needed.
Figure 9. Example of comparison of
the annual running and periodic replacement costs for different level of renovation
EN 15459-1 is a powerful tool for the decision making process with many possible applications. It allows the comparison of different solutions and find the most effective approach for building owner for renovation or new building construction towards NZEB.
The specific of this standard is that many inputs are not as exact as for energy performance calculation because of uncertainty of several inputs looking far in the future. Economic results are closely related to the project under consideration, and it may be difficult to make general conclusion. Consideration of different scenarios is therefore recommended in the daily professional work for risk mitigation.
The corrections needed in the standard, discovered during the development of the CEN-CE training, are addressed and corrected in the training materials. The proposal for changes will be delivered for the next revision of this standard. The non-energy benefits as better commercialisation of building due to attractiveness and better indoor environment quality will be also recommended to be considered for future revision of this standard.
[1] Directive 2010/31/EU of the European Parliament and of the Council of 19 May 2010 on the energy performance of buildings, amended by Directive (EU) 2018/844 of the European Parliament and of the Council of 30 May 2018 amending Directive 2010/31/EU on the energy performance of buildings and Directive 2012/27/EU on energy efficiency,
[2] The Commission delegated regulation (EU) No. 244/2012 supplementing Directive 2010/31/EU of the European Parliament and of the Council on the energy performance of buildings by establishing a comparative methodology framework for calculating cost-optimal levels of minimum energy performance requirements for buildings and building elements.
[3] EN ISO 52000-1:2017 - Energy performance of buildings — Overarching EPB assessment — Part 1: General framework and procedures
[4] EN 15459-1:2017 - Energy performance of buildings - Economic evaluation procedure for energy systems in buildings - Part 1: Calculation procedures
[5] CEN-CE, Horizon 2020 project, www.cen-ce.eu