Stay Informed
Follow us on social media accounts to stay up to date with REHVA actualities
Jörgen ErikssonLic.Sc. (Tech.), Senior Consultant, | Max
TillbergM.Sc.
Senior Consultant, |
This case
study is made with the purpose to create a plant model that can serve as a test
bench for model predictive control systems. The plant consists of ground source
heat exchangers and heat pumps that deliver heat and cooling to a small
district. These major components are calibrated using measured data from the
actual plant. This article is focused on the validation of the total plant
model. Measurements of delivered heating and cooling from the plant in
operation are used as input to the simulation model that shows good agreement
with the measurements.
Model
predictive control systems uses models as a part of control algorithm. These
models are used with some sort of optimization algorithm to present the best
momentarily control action that, for example, gives the lowest expected energy
use over the next year. This case study is made in the framework of the
research project DEBORAH with the purpose to create a plant model that can
serve as a test bench for such control systems. The plant as seen in Figure 1 is owned by Husvärden AB in Mölndal Sweden and delivers heating and cooling to a mix of
newly built apartment buildings, commercial buildings and old refurbished
industrial buildings converted to commercial buildings.
Figure 1.
Simulation model of plant. A few components are removed to increase its
readability. The model is based on a schematic drawing (Bengt Dahlgren AB) of
the plant. The main features pointed out. (1) Three 500 kW Heat pumps. (2)
Five 10 m tanks. (3) Two separate groups of GSHX, 80 holes (in use
since 2015) and 35 holes (in use since 2018). (4) Dry cooler, 665 kW.
All energy meters are marked with (5).
The plant
is built up around three 500 kW heat pumps (1) that use two set of ground
source heat exchangers (3) of 80 holes and 35 holes respectively as
main source for collecting heat. However, during the summer the cooling system
of the buildings is used as source for the heat pumps. As the use for heat is
limited in the summer a 665 kW dry cooler (4) is
installed to reject the surplus heat. To even out the heat load on the hot
side, there are five tanks (2) of 10 m³ each.
The study
was carried out using the following workflow with five steps:
Step 1. Based on drawings and control description
from the plant designer, a first model of the plant was created using standard
models of IDA ICE.
Step 2. The initial simulations of the plant model
were analyzed to see if the standard models of IDA ICE were suitable for
this study or if additional models had to be created. During this step three
models were identified that had to be created:
ü The first model was a heat pump. The
heat pump manufacturer didn’t provide the type of data needed to use the standard
heat pump model included in IDA ICE.
ü The second model was a model of
tanks coupled in series. This model was needed due to loading/unloading through
the same pipes creating reversible flows which isn’t allowed in the standard
models of IDA ICE.
ü The third model needed was a
simplified borehole model that could be calibrated with reasonable effort. The
advanced model in IDA ICE was too detailed to be calibrated when the
number of holes is as large as in this study.
Step 3. To extract measurements from the plant a
SQL database was created. Measurements from the control system was logged to
the data base with 10 minutes sampling time. From the control system about
200 points from temperature sensors, valve positions and fluid flows were
logged. The heat pumps are equipped with a tool for analyzing their
performance, ClimaCheck. From this system about 156 data
points of more detailed information about the heat pumps were logged, COP for
each compressor, energy used by each compressor, evaporator and condenser
temperatures etc.
Step 4. The system of ground source heat
exchangers and the heat pumps needed to be calibrated before the model of the
plant could be expected to cope with the measurements. The data set for
calibration was from the period Jan 1st 2018 to June 30th 2018.
Step 5. To verify if the simulation model of the
plant is valid to use as a test bench two cases were simulated using the
calibrated subsystems from step 4. During this step a data set of
measurements ranging from July 1st 2018 to April 30th 2019 was used. In the first set-up, Case 1,
the simulation model was controlled by measured signals of control signal to
the heat pumps, valve positions and fluid flows. In the second set-up, Case 2,
the plant was simulated using simulated control based on the control
description from the plant designer.
The first
of the two sub systems to be calibrated was the ground source heat exchanger.
In Figure 2, the IDA ICE model used for
GSHX calibration is shown.
Figure 2.
The set-up of the calibration model of the GSHX using IDA ICE.
The fluid
flow and supply temperature to the ground was used as input. Then the integral
of the difference between calculated and simulated return temperature from the
ground was used as an objective function to be minimized.
The ground
source heat exchangers needed to be calibrated for two reasons. The first
reason is the deviations between the proposed layout of the bore holes and the
actual bore holes drilled. Also, although there are thermal response tests
(TRT) performed on the site, the site is so large that they can’t represent the
entire site. The second reason is that there are two different sets of boreholes
that were taken into use at different stages. The first set of 80 holes
with single U-pipes were taken in to use 2015 and the second set of 35 holes
with double U-pipes a few years later, 2017. The usage history of mostly the
first set was unknown when the measurements started. Hence, there are two
problems in one. Estimating the temperatures in the ground to be used as
starting point for the simulation and calibrating the performance of the GSHX.
Looking at hourly mean values of the return temperature from the ground, the
maximum deviation between the calibrated model and the measurements, is about ±0.4°C.
The three
heat pumps have two compressors each which are used according to an internal
control system. This internal control makes the calibration of them important
as there is no information available describing this control. In Table 1 some of the results from the calibration are shown. As can be seen the
difference between the calibrated and un-calibrated models is substantial.
Table 1.
Results from calibration of heat pumps. The deviation calculated is difference
in energy during the simulated period. The deviation before calibration is
quite different among the heat pumps. After the calibration the deviation is
less than 1% for all cases.
Heat
pump 1 | Heat
pump 2 | Heat
pump 3 | |
Evaporator energy | |||
Uncalibrated, % | 8.2 | 0.2 | 18 |
Calibrated, % | −0.026 | 0.224 | 0.178 |
Compressor energy | |||
Uncalibrated, % | 4.3 | 8.3 | 8.6 |
Calibrated, % | 0.499 | −0.959 | 0.187 |
Figure 3.
An example of model behavior before and after calibration. The catalog data
implied better performance at part load than the actual performance.
The final
step in this study was to see if the simulation of the entire plant could match
the reality. To do this, two cases was studied. In Case 1, the plant was
controlled by measured signals and in Case 2, the plant was controlled
using a simulated control based on information from the control description. As
driving data for the simulation, the return temperature and mass flow from the
heating circuit and the cooling circuit are used. To verify the performance, the
measured heating and cooling power are used to compare the simulation result
with the measurements. In Figure 1, the simulated plant is shown.
In Case 1,
the simulation is performed using measured signals to control the plant. In Figure 1, at each point where “Ctrl” is written in blue, a signal from the
measurements is used. The signals used are control signals to the heat pumps
and valves and where available the actual fluid flow. The fluid flow is
available at each point where an energy meter is located, see Figure 1. The comparison of delivered heat and cooling between measurements and
simulation is shown in Figure 4. The mean error during the
simulated period is 5.1% for delivered heat and 1.4% for delivered cooling. Due
to measurement problems the compressor power was only logged from April 3rd.
The mean error during this period was 6.6%. A more detailed analysis shows that
the larger errors occur at small compressor powers.
In Case 2,
the simulation is performed using simulated control. However, the actual
setpoint signals for the supply temperature for heating and cooling are used in
the control. In the results below shown in Figure 4, the error is less than in Case 1.
The mean error during the simulated period is −0.7% for delivered heat
and 1.3% for delivered cooling This is due to the simulated control that
corrects for some of the modelling faults.
Figure 4.
The graphs show the daily mean of the supplied heating and cooling from the
plant. Red is measured data. Green represent Case 1 and blue Case 2.
Was a
calibration of the subsystems really needed? To answer that question a
complimentary simulation was performed equal to Case 1 with measured
signals as control but leaving the heat pumps uncalibrated. The deviation
during the simulation period regarding heat delivered from the plant is 18%, it
can be seen quite clear in Figure 5. The compressor energy of April had
an 8% error which is similar as with the calibrated model. This implies a
better COP in the model than the measurements.
Figure 5.
Results comparing the case with uncalibrated heat pumps to the measurements.
The result
states that it is possible to create reliable simulation models of small
district plants using IDA ICE and the model provides a perfect test bench
for alternative controls. In this kind of system where a measured load is used,
the driving data for plant simulation must contain the return temperature
otherwise the temperature level of the system may drift. As heat pumps have
internal control, a simulation model needs calibration to capture their real
performance.
Follow us on social media accounts to stay up to date with REHVA actualities
0